| Thickness | Sq Feet / Hour | Sq Meters / Hour |
|
4" - (102mm) |
8,100 to 11,700 |
750 to 1,090 |
Information
listed in this CONCRETE BREAKING PRODUCTIVITY CHART was gathered from many years
of operational experience and confirmed by recent nationwide surveys. This
data is a guide to determining average concrete breaking production for a
specified thickness. A number of factors must be taken into
consideration: age and composition of the concrete, rebar, hardeners and
type of aggregate used.
COMPACTION IN NARROW PLACES
- Layers of 3ft to 6ft at 95% to 100%
efficiency
Applications include: Foundations & Trenches.
|
Backfill: |
Cu Yards / Hour | Cu Meters / Hour |
| Cohesive soils | 46 | 42 |
| Well Graded Granular Soils | 22 | 20 |
| Uniformly Graded Backfill | 17 | 15.5 |
TRENCH CUTTING
| Asphalt Thickness | 4" (10cm) |
6" (15cm) |
8" (20cm) |
10" (25.4cm) |
12" (30.5cm) |
14" (35.5cm) |
| Linear Feet/Hour (Meters)/Hour |
225' (68m) |
210' (64m) |
195' (60m) |
180' (55m) |
165' (50m) |
150' (46m) |
![]()